Complete studies of the wastewater treatment plant building

Construction of the Sart-Dames-Avelines purification plant Purification plant with a capacity for 2,900 PE. It is a low-rate activated sludge plant with nitrification and denitrification Excess sludge is thickened statically and stored in a sludge silo The project designer assignment awarded to TPF-Utilities includes the following design projects:

  • Preliminary designs and outline plan: determining the population equivalent number to be taken up by the plant, dimensioning new equipment and facilities, estimating the cost of the investment and the operating costs, …
  • Drafting the specifications, that is to say, the administrative terms and conditions, general terms and conditions for civil engineering and electromechanical equipment, special technical terms and conditions and the related appendices (tender documentation, estimate to be completed, etc.)
  • Analysis of tenderers’ bids and drafting the award report.
  • Management of works, including: planning follow-up, verification of civil engineering and electromechanical technical proposals, checking the proper execution of works, progress approval and final statement, etc.

Client

Intercommunale du Brabant Wallon (IBW)

Project Dates

2007 – 2014