Complete studies of the wastewater treatment plant building

Construction and commissioning of the Louvain-la-Neuve purification plant.
In response to the constraints on the variability of the rate to be processed, required performance levels and surface area available, the process using Membrane bioreactor (MBR) has been selected.
Nominal capacity of the plant: 12 000 PE in DBO5.
Flow treated: 1 700 m³/j, Q18 = 100 m³/h.
Total membrane surface: 6,048 m².

The project designer assignment awarded to TPF-Utilities includes the following design projects:

  • Preliminary designs and outline plan: determining the population equivalent number to be taken up by the plant, dimensioning new equipment and facilities, estimating the cost of the investment and the operating costs, …
  • Drafting the specifications, that is to say, the administrative terms and conditions, general terms and conditions for civil engineering and electromechanical equipment, special technical terms and conditions and the related appendices (tender documentation, estimate to be completed, etc.)
  • Analysis of tenderers’ bids and drafting the award report.
  • Management of works, including: planning follow-up, verification of civil engineering and electromechanical FT, checking the proper execution of works, progress approval and final statement, etc.

Client

Intercommunale du Brabant Wallon (IBW)

Project Dates

2003 – 2008