The extension of line A of Mexico City Metro has a total length of 13 km between the current terminus La Paz and the new terminus Chalco. The action aims to develop seven new stations, including the terminal. It includes the execution of an auxiliary facilities area or depot area.

It includes the coordination of the work required to justify the technical feasibility of the project in particular the following tasks with a draft design approach:

  • Geometrical design ( plan, elevation and section type )
  • Railway Project ( connection to current line , switches scheme)
  • Architectural design of stations and terminals
  • Civil engineering budget, construction procedures and works planning
  • Operational and functional Scheme
  • Operation and Maintenance Manual
  • Definition of indicators and performance levels

Client

DYSA, Desarrollo y Servicios Aeronáuticos, S.A. de C.V.

Project Dates

2014

Project Figures

  • Approximate value of services provided: 94,697 € (VAT included)
  • Total amount of investment: 662 millon euros (VAT included)