Heavy storms during winter of 2012 affected severely the infrastructure intended for protection of one of the most colourful beach resort at the Black Sea, Costinesti, destroying along the way part of the beach itself.

The repairs to the protection breakwater in Costinesti, were completed during April 2014, works designed by TPF CPROJECT’s engineers for the Basin Water Administration – Dobrogea-Seashore.

The breakwater needed complete restructure of the raw stone on the entire length of the gap created during the flooding and restoration of the articulated concrete blocks shell. Works included concreting the crowning slab to secure protection against erosion, restoration of stone core and rearrangement of stone protection coat.

Client

Basin Water Administration – Dobrogea-Seashore

Project Dates

2013 – 2014

Partners

SCIM SA (general contractor)