GETINSA - Detailed design of the upgrading works of road 25, between Chulumani and Sacambaya

The contract included: coordination of the different elements of the project; financial management and control; review of technical elements; improvements to the alignment and drainage; design of new structures; land survey; soil mapping; geological and geotechnical surveys; traffic study; pavement design; socioeconomic study and study of environmental measures.

Client

Administradora Boliviana de Carreteras (National Road Agency). Gerencia Regional La Paz (La Paz Regional Management)

Project Dates

2012 – 2013

Partners

CONIN SRL

Project Figures

Contract Value:
1,170,936 USD