Construction of a solar PV park in Arsac near Bordeaux with a capacity of 85 MW and an area of 160 hectares

TPF Ingénierie has been entrusted  for the scheduling – control – coordination mission (OPC). It is a challenging task in many ways as the park has to be realized within 6 months.

Tracking from shipment to delivery the  supplies from China and managing the on-site storage represent a major challenge in order to keep the timetable and to ensure that the facility is successfully built.

All the photovoltaic modules  which represent  together 433 containers  and connection elements are delieved on a just-in-time basis by sea, via the port of Antwerp to the port of Verdon-sur-Mer, 80 km from the site.

Client

Solairedirect

Project Dates

Delivery: 2015